Skip to content Skip to left sidebar Skip to right sidebar Skip to footer

Tag: paving

Cranford Avenue Resurfacing

Please be advised that concrete work (handicap ramps, curbs and sidewalks damaged by city tree) will commence on Monday, July 29th, 2019 for the above referenced project.

We estimate 2-3 weeks (weather permitting) for this work followed by milling and paving.

Flyers have been distributed to the residents.

The LPD Traffic Bureau will be posting Emergency No Parking Signs.

The roadway will be open to traffic at this time while work is performed on one side at a time.

An Inspector from the Engineering Department will be onsite a majority of the time.

The main contractor is DLS Contracting and his concrete sub is FDM.

Please advise the Engineering Department of any concerns.

All DPW garbage, recycling and trash pickups will remain the same.